A reused vessel, a capped tax holiday and a far stronger project: what the numbers published on 26 November 2026 say about GLIAG’s 2 July 2026 screening model, and what they mean for Suriname
On 26 November 2026 PETRONAS and Staatsolie took the Final Investment Decision for the Sloanea gas field in Block 52, now named KrakaWi (“supports us” in Sranan Tongo). The published numbers confirm the direction of GLIAG’s 2 July 2026 essay and overturn most of its economics [12]. The tax holiday was a bankability tool, FID came in H2 2026 and first gas is set for mid-2030: all three calls held. The capex assumption did not. GLIAG’s July GLIAGOGRAPH put the FLNG alone above US$4.0 billion for 2.0 MTPA. The FID puts the whole project, wells and subsea included, at US$1.6 billion for about 1.5 MTPA [15].
Re-running the screening model on FID terms lifts the project IRR at a US$10/MMBtu netback from 11.3% to 19.4% without a holiday and from 14.0% to 22.2% with the holiday as agreed. The holiday itself also changed. It is no longer a flat ten years. It ends once the investor has recovered twice its investment, which at US$10 means roughly 5.5 to 6.5 years and at today’s prices 3 to 4 years, according to Staatsolie’s managing director Annand Jagesar [5]. State take over 25 years comes out at US$6.07 billion before profit gas, against the US$6 billion Jagesar gave at the press conference. July’s US$0.9 to 1.6 billion was too low by a factor of four or more.
One sentence from the press conference carries the economics. Jagesar said costs are much lower because PETRONAS is using an existing floating LNG unit, and that a new-build facility would have put the investment at about US$3.5 billion [5]. On that new-build figure the model gives a capped-holiday IRR of 10.9% and 9.3% without the holiday, barely at the 10% real hurdle. Vessel reuse is what makes KrakaWi a sound project. The holiday buys speed and financing comfort for a first-of-its-kind development, at a cost to the State of about US$0.6 billion over field life at US$10.
The question for Suriname now moves to two places. The first is the gas the vessel does not use: on the published volumes about 1.5 Tcf of recoverable gas sits outside the 25-year FLNG plan (section 8). The second is the larger second gas project, where the domestic gas and Gas-to-Shore terms have to be fixed before the development plan is filed.
Tan Sri Tengku Muhammad Taufik, President and Group CEO of PETRONAS, and Annand Jagesar, Managing Director of Staatsolie, presented the milestone to President Jennifer Geerlings-Simons at the Presidential Palace in Paramaribo [15]. Vice President Gregory Rusland and the ministers Patrick Brunings (Oil, Gas and Environment) and David Abiamofo (Natural Resources) attended [1]. Staatsolie approved the Field Development Plan on 24 November 2026 [15]. The operators’ joint release, PETRONAS’ own release and the Government release now agree on the core figures [1][15][17], so the table below is a published record and no longer a press reading.
| Item | Published figure | Source |
|---|---|---|
| Project | Sloanea gas field, Block 52, named KrakaWi (Sranan Tongo: “supports us”; Kraka = supports, Wi = we/us) | Staatsolie [15][16] |
| Concept | 4 offshore production wells, subsea infrastructure, floating LNG; LNG exported by ship | Staatsolie [15]; gov.sr [1] |
| FLNG | About 1.5 million tonnes of LNG a year; an existing PETRONAS floating LNG unit, not a new-build (vessel not named) | [15]; Jagesar, Starnieuws [5] |
| Investment | US$1.6 billion initial investment; new-build alternative about US$3.5 billion; Staatsolie co-invests pro rata, US$320 million | [15]; [5]; Reuters [18] |
| Staatsolie financing | Arranged through an existing loan facility; held through Paradise Oil Company | Reuters [18]; [5] |
| First gas · life | Mid-2030; PETRONAS targets H1 2030 · 25 years | [15]; [18] |
| Gas volumes | 97 bcm (3.43 Tcf) recoverable; nearly 4 Tcf resources and 2 Tcf reserves (Taufik) | [15]; [6][19] |
| Tax holiday | Maximum 10 years; ends earlier once the investor has recovered 2× its investment; 3 to 4 years at current prices | Jagesar [5] |
| Fiscal basis | PSC of 2013 allows separate fiscal terms for non-associated gas; oil-based terms gave insufficient return | Jagesar [5]; [15] |
| State revenue | Royalties (6.25% of production, profit or not), State share of production revenue (profit gas, split not disclosed) and taxes; about US$6 billion over 25 years | [15]; Jagesar [5] |
| Equity | PETRONAS Suriname E&P B.V. 80% (operator); Staatsolie, through Paradise Oil Company, 20% | [15]; [8] |
| History | PSC 2013; Sloanea-1 discovery late 2020; Sloanea-2 appraisal and well tests 2024; Commercial Field approved 11 Nov 2025; FDP approved 24 Nov 2026 | [15]; [9] |
| Next projects | Second gas project at least twice KrakaWi; oil project in preparation; PETRONAS active in 8 blocks; Block 52 holds more than 1 billion boe; Block 66 (Senna, Picolet, about 1 billion boe potential) drilling | [3]; Reuters [18] |
| Gas-to-Shore | Not part of this FID. Simons: “Gas-to-Shore gaan we zeker doen”; method, timing and partners still to be worked out | [4] |
Three statements matter for the doctrine. Jagesar said the field could not have been developed commercially without adjusted fiscal terms, because calculations on the existing oil terms gave insufficient return: the July essay’s bankability thesis in his own words (reported speech, [5]). In the joint release he added that without gas processing oil cannot be produced from certain reservoirs, and that Suriname can start preparing to bring gas onshore for “more and cleaner electricity” [15]. PETRONAS, for its part, described Block 52 as part of the Golden Lane, the corridor where much of Suriname’s oil and gas potential remains undeveloped [3]. The author introduced that term for the Guyana–Suriname fairway in 2008.
Each line of the 2 July 2026 essay and its GLIAGOGRAPH is set against the published figure or, where the FID gives no number, against GLIAG’s re-engineered model (section 4). CONFIRMED means the July call stands. REVISED means the direction held and the number moved. CORRECTED means the July figure or treatment was wrong.
| Item | 2 July 2026 | 26 Nov 2026 / GLIAG | Difference | Verdict |
|---|---|---|---|---|
| FID timing | H2 2026 | FID announced 26 Nov 2026 | On target | CONFIRMED |
| Development concept | Gas wells + subsea + FLNG | 4 production wells + subsea + FLNG | Well count added | CONFIRMED |
| FLNG capacity | 2.0 MTPA | ~1.5 MTPA | −0.5 MTPA (−25%) | REVISED |
| Plateau feed gas | ~300 MMscf/d | ~231 MMscf/d (GLIAG, derived) | −69 MMscf/d (−23%) | REVISED |
| Capex | FLNG alone > US$4.0 bn (new-build) | US$1.6 bn total, existing FLNG; new-build ~US$3.5 bn | −US$2.4 bn or more (−60%) | CORRECTED |
| Staatsolie (POC) share | 20% profit oil, no capex shown | 20% equity; pays US$320 m | Paying partner, not free share | CORRECTED |
| First gas | ~2030 | Mid-2030; H1 2030 targeted | Narrowed | CONFIRMED |
| Project life | 20 years (2030–2049) | 25 years (2030–2054) | +5 years | REVISED |
| Gas volume basis | ≈2.05 Tcf feed gas; 2.5–3.0 Tcf for comfort | ~2 Tcf reserves; ~4 Tcf resources; 97 bcm (3.43 Tcf) recoverable | Resource base exceeds comfort band | CONFIRMED |
| Tax holiday | 10 years, flat | Max. 10 years; ends at 2× investment recovered | Capped by recovery | CORRECTED |
| Holiday duration | 10 years | 3–4 yrs at current prices (Jagesar); 5.5–6.5 yrs GLIAG at US$10 | −3.5 to −7 years | CORRECTED |
| Royalty | 6.25% of gross | 6.25% on production | None | CONFIRMED |
| Equity | PETRONAS 80% / POC 20% | PETRONAS 80% / POC 20% | None | CONFIRMED |
| Project IRR, no holiday | 11.3% | 19.4% (GLIAG, US$10) | +8.1 pp | REVISED |
| Project IRR, with holiday | 14.0% | 22.2% (GLIAG, capped, US$10) | +8.2 pp | REVISED |
| Holiday IRR uplift | +2.7 pp | +2.8 pp | +0.1 pp | CONFIRMED |
| NPV10, with holiday | US$1.17 bn | US$1.56 bn (GLIAG) | +US$0.39 bn | REVISED |
| Breakeven LNG netback | US$7.0–8.3/MMBtu | US$5.5–5.9/MMBtu (GLIAG) | −US$1.5 to −2.4 | REVISED |
| State take, life of field | US$0.88–1.58 bn (20 yrs) | US$6.1 bn (GLIAG, 25 yrs); US$6 bn (Jagesar) | ×4 to ×7 | CORRECTED |
| Cost of holiday to State | ≈US$0.70 bn | ≈US$0.60 bn (capped); US$1.10 bn if flat | −US$0.10 bn | REVISED |
| Bankability thesis | Holiday is a bankability tool | ‘Not viable on oil-based terms without adjusted fiscal terms’ (Jagesar, reported) | None | CONFIRMED |
| Block 52 as gas province | Sloanea success de-risks Block 52 | Second gas project ≥2× KrakaWi; oil project in preparation | Ahead of prognosis | CONFIRMED |
| Gas-to-Shore | Future option | Not in FID; government: ‘Gas-to-Shore gaan we zeker doen’ | Still open | CONFIRMED |
Score: 10 confirmed, 8 revised, 5 corrected out of 23 items. The strategic calls were right. The cost and fiscal inputs were not.
Strict reading. The scoring above is generous to July in one respect. Erratum 4 (section 3) shows that the July IRR, NPV and breakeven could not be reproduced from July’s own inputs. A number that was irreproducible on the day of publication cannot be “revised” by a later event; strictly it was wrong. Moving IRR (two lines), NPV10, breakeven and the holiday uplift into the corrected column gives about 10 confirmed, 4 revised, 9 corrected, if the uplift line is also treated as unproven. The +2.7 pp against +2.8 pp match on the holiday uplift may be coincidence: it was computed on a base that does not close. GLIAG reports both scores and relies on neither for the strategic argument.
An audit that only compares a forecast with outcomes misses errors that were visible on the day of publication. A second pass through the July GLIAGOGRAPH finds five that GLIAG reports openly here.
None of these errors changes the July essay’s argument, which was qualitative and has been confirmed. They do change every number that came with it. The re-engineered model below replaces them. For this edition GLIAG rebuilt that model a second time, independently and from the stated inputs only; the rebuild reproduces every result in sections 4 and 5 to the published decimal.
The model keeps the July price and cost basis so that the comparison isolates what the FID changed: LNG netback US$10/MMBtu real 2026, opex US$2.0/MMBtu, royalty 6.25% of gross, income tax 36% with five-year straight-line depreciation from first gas, 10% real discount rate to 2026. The FID inputs are 1.5 MTPA nameplate (78 million MMBtu of LNG a year at 52 MMBtu/tonne), US$1.6 billion capex phased 2027–2030 (30/35/25/10%), first gas mid-2030, plateau 2032–2050 and decline to 2054. Feed gas at plateau is about 231 MMscf/d and cumulative feed gas 1.89 Tcf, in line with the 2 Tcf of reserves Taufik cited. Profit gas, sustaining capex, abandonment and financing costs are excluded. The US$1.6 billion is the initial investment [5]; later wells or compression would come on top.
Read the results as bounds. Because profit gas is excluded, every State-take figure in this essay is a floor and every contractor IRR is a ceiling. Section 4.4 shows how far each moves once a profit-gas split is applied.
| Indicator at US$10/MMBtu | No holiday | Capped holiday (FID) | Flat 10 years (July basis) |
|---|---|---|---|
| Project IRR | 19.4% | 22.2% | 23.2% |
| NPV10, US$ bn (2026) | 1.22 | 1.56 | 1.76 |
| Payback from first gas, years | 4.5 | 3.5 | 3.5 |
| Gross revenue 2030–54, US$ bn | 17.52 | 17.52 | 17.52 |
| Royalty 6.25%, US$ bn | 1.10 | 1.10 | 1.10 |
| Income tax 36%, US$ bn | 4.14 | 3.39 | 2.77 |
| Staatsolie 20% net of US$320 m, US$ bn | 1.44 | 1.59 | 1.71 |
| State take excl. profit gas, US$ bn | 6.67 | 6.07 | 5.57 |
| State take, % of gross | 38.1% | 34.6% | 31.8% |
Three numbers carry the argument. First, the project clears a 10% real hurdle without any holiday, with a breakeven netback of US$5.9/MMBtu, against US$8.3 in July. Second, the holiday adds 2.8 percentage points of IRR. Third, State take of US$6.07 billion at US$10 lies close to Jagesar’s US$6 billion.
That third match is not a validation. Jagesar’s figure includes profit gas, and its price deck is not published. The same reported statement puts the holiday at 3 to 4 years “at current prices”; in this model a holiday that short needs a netback of about US$14 to US$18, where State take before profit gas would already be US$9.7 to 13.2 billion. The US$6 billion is therefore more consistent with a long-run price well below today’s, or with a modest profit-gas share at about US$8.5 (a 30% State share gives US$6.08 billion there). GLIAG’s view is that the two numbers describe the same order of magnitude, not the same project terms [VERIFY].
| Netback, US$/MMBtu | IRR, no holiday | IRR, capped | NPV10 capped, US$ bn | State take capped, US$ bn |
|---|---|---|---|---|
| US$8 | 15.4% | 17.8% | 0.94 | 4.26 |
| US$10 | 19.4% | 22.2% | 1.56 | 6.07 |
| US$12 | 23.0% | 26.3% | 2.19 | 7.84 |
| US$14 | 26.2% | 29.6% | 2.77 | 9.70 |
| Capex case at US$10 | Capex, US$ bn | IRR, no holiday | IRR, capped | NPV10 capped, US$ bn | State take capped, US$ bn |
|---|---|---|---|---|---|
| FID, existing FLNG | 1.60 | 19.4% | 22.2% | 1.56 | 6.07 |
| +40% overrun | 2.24 | 14.9% | 17.1% | 1.18 | 5.61 |
| Capex doubled | 3.20 | 10.4% | 12.1% | 0.45 | 5.25 |
| New-build FLNG (Jagesar) | 3.50 | 9.3% | 10.9% | 0.21 | 5.19 |
| New-build, upper | 3.60 | 9.0% | 10.5% | 0.13 | 5.17 |
On the new-build figure the holiday runs its full ten years, because 2× recovery of US$3.5 billion is not reached before 2039. The project then sits at the hurdle with the holiday and below it without. This is the quantitative content of Jagesar’s statement: the existing vessel is worth about US$1.9 billion of capex and about 11 points of IRR.
The split of profit gas has not been published. To show its weight, the model applies a cost-gas ceiling of 80% of revenue after royalty and a State share of the remaining profit gas of 10%, 30% or 50%, with income tax charged on the contractor’s share. These are GLIAG test values, not the PSC terms [VERIFY].
| State share of profit gas (US$10, capped holiday) | 0% (base) | 10% | 30% | 50% |
|---|---|---|---|---|
| Contractor project IRR | 22.2% | 21.1% | 19.1% | 16.6% |
| NPV10, US$ bn | 1.56 | 1.37 | 1.02 | 0.67 |
| State take incl. profit gas, US$ bn | 6.07 | 6.70 | 7.86 | 8.99 |
| State take, % of gross | 34.6% | 38.3% | 44.8% | 51.3% |
Even a 50% State share of profit gas leaves the contractor above 16% at US$10. On these numbers Suriname had room to ask for a meaningful profit-gas share on top of the capped holiday. Whether it did is the first number Parliament should request.
The July essay treated the holiday as ten fixed years. The agreed version is a payback clock: it stops when the investor has earned back twice its outlay, with ten years as the ceiling [5]. High prices now shorten the holiday instead of enriching it, which moves price risk back to where it belongs.
The published terms do not say whether “recovered” means cumulative operating cash flow or gross revenue. GLIAG ran both. At US$10/MMBtu the holiday lasts 6.5 years on the cash-flow reading and 5.5 years on the revenue reading. At US$14 it falls to 4.5 and 3.5 years, which brackets Jagesar’s “three to four years at current prices”. The definition is worth about US$0.17 billion of State take at US$10 and should be published [VERIFY].
Cost to the State, measured against no holiday: US$0.60 billion over field life at US$10 with the cap, against US$1.10 billion for a flat ten years. The cap saves Suriname about US$0.5 billion compared with the version July modelled.
US$1.6 billion for 1.5 MTPA is about US$1,067 per tonne of annual capacity, with wells and subsea included. The draft of this essay read that figure as a sign of a reused or converted hull. Jagesar has since confirmed it: PETRONAS is using an existing floating LNG unit, and a new-build would have cost about US$3.5 billion [5].
| Benchmark | Scope | US$ per tonne a year | Source |
|---|---|---|---|
| KrakaWi FID (existing FLNG) | Wells, subsea, FLNG | ~1,067 | [15] |
| KrakaWi new-build (Jagesar) | Wells, subsea, new FLNG | ~2,333 | [5] |
| Golar MKII conversion (Fuji) | FLNG conversion, vessel only | ~620 | Gas Strategies [10] |
| Woodside Louisiana LNG | Onshore liquefaction only | ~960 | Gas Strategies [10] |
The capacity points to PETRONAS’ second floating unit, PFLNG DUA, with a nameplate of 1.5 MTPA [11]. GLIAG’s 20 November 2026 essay examined DUA’s redeployment as an option for Sloanea [13]. The operators have not named the vessel, so the identification stays GLIAG judgement [VERIFY]. Two items remain open. How the existing unit enters the project accounts (transfer at book value, lease or charter) determines whether part of its cost sits in opex; a charter would lower the IRRs above by the charter rate. And a reused hull carries refurbishment, life-extension and class-renewal costs over a 25-year field life that a new-build would not.
President Simons announced a revised Savings and Stabilization Fund law with three components (savings and stabilization, national development investment, social provisions) plus a housing fund for low-interest loans and a health fund for universal access to care [4]. KrakaWi revenue from 2030 will be the first gas-based inflow to test that architecture. On local content, the Government has agreed training and certification support with PETRONAS; some 900 to 1,200 people have been trained through SAO, with a target of 3,000. The Local Content Board is to report before the end of 2026, Minister Brunings expects to publish labour-demand data in Q1 2027, and the Government hopes the supplementary oil and gas legislation passes the National Assembly in 2027 [4].
The FID record carries three volume figures that are often quoted as one: about 2 Tcf of reserves and nearly 4 Tcf of resources (Taufik [6][19]) and 97 bcm, or 3.43 Tcf, of recoverable gas (Staatsolie, gov.sr [1][15]). The model’s 25-year FLNG throughput, at 1.5 MTPA and 10% fuel and shrinkage, is 1.89 Tcf of feed gas. That matches the reserves figure. It also leaves about 1.5 Tcf of recoverable gas outside the vessel plan.
Spread over 25 years, 1.5 Tcf is about 165 MMscf/d. For scale, a 400 MW combined-cycle power plant at full load and a heat rate of 7,000 Btu/kWh burns about 65 MMscf/d (GLIAG model). GLIAG’s view is that this headroom is the first candidate volume for Gas-to-Shore. It may instead be meant for a later FLNG life extension, a second train or reinjection, or the difference may be one of definitions between reserves and recoverable volumes. None of this is in the public record.
The question for Parliament is simple: who holds the right to the recoverable gas the vessel will not process, and on what terms can it be brought onshore? It belongs alongside the profit-gas split as the second number to request.
KrakaWi liquefies every molecule offshore and ships it out. That was the design from the start, and the FID does not change it. Vice President Rusland said Gas-to-Shore should be the basis for further industrialization and that Suriname must avoid the path of resource-rich countries whose citizens hardly benefit; Simons said it will be done, with method, timing and partners still to be worked out, and that there is no concrete plan for joint gas development with Guyana [4]. Jagesar framed onshore gas as a preparation step for more and cleaner electricity [15]. The Sovereign Molecule™ is GLIAG’s term for the national claim on domestic use of the State’s gas before export.
The opening is the second gas project, which PETRONAS sizes at at least twice KrakaWi [3], and the 1.5 Tcf headroom in section 8. Under GLIAG’s National Pre-FID Gate doctrine, three conditions belong in that project’s development plan before Staatsolie approves it:
Without these terms in the plan, the second project will copy KrakaWi’s export-only design, and Suriname’s Sovereign Conversion Capacity™, GLIAG’s measure of installed onshore capacity to turn gas into power, industry and products, stays at zero for another decade. The New Refinery and Gas-to-Shore Pre-FS are GLIAG proposals, not sanctioned projects.
| FACT | MISSING | GLIAG JUDGEMENT | TRIGGER |
|---|---|---|---|
| US$1.6 bn initial investment; existing FLNG; new-build ~US$3.5 bn [5][15] | Vessel name; transfer, lease or charter basis; life-extension cost | Reuse is load-bearing: worth ~11 points of IRR | Charter rate published or vessel named |
| Holiday max. 10 yrs, ends at 2× recovery [5] | Definition of “recovered” | Cash-flow reading: 6.5 yrs at US$10; ±US$0.17 bn State take | Fiscal terms laid before Parliament |
| State share of production revenue exists [15] | Profit-gas split and cost-gas ceiling | US$6.07 bn is a floor; contractor IRR a ceiling | Split disclosed; re-run section 4.4 |
| 97 bcm (3.43 Tcf) recoverable; 2 Tcf reserves [6][15] | Who holds rights to the ~1.5 Tcf not processed | First candidate volume for Gas-to-Shore | FDP summary or reserve report published |
| Second gas project ≥2× KrakaWi [3] | Domestic-gas clause, tariff, priority rules | The Pre-FID Gate must apply before its FDP | FDP filing for project two |
| Jagesar: ~US$6 bn over 25 yrs [5] | Price deck; profit-gas inclusion | Same order of magnitude, not a validation | Staatsolie publishes its assumptions |
| Driver | Range tested | Effect on capped IRR / State take |
|---|---|---|
| LNG netback | US$8 to US$14/MMBtu | IRR 17.8% to 29.6%; State US$4.26 to 9.70 bn |
| Capex | US$1.6 to US$3.6 bn | IRR 22.2% to 10.5%; new-build at the hurdle |
| Holiday trigger definition | Cash flow vs revenue | Holiday 6.5 vs 5.5 yrs at US$10; State ±US$0.17 bn |
| Profit gas split | 0% to 50% State share (illustrative) | State US$6.07 to 8.99 bn; IRR 22.2% to 16.6% [VERIFY] |
| FLNG ownership | Owned vs chartered | Charter moves cost into opex and lowers IRR [VERIFY] |
| First-gas timing | One-year delay | IRR unchanged in real terms; NPV10 1.56 to 1.42 bn |
What would change the view: an operator disclosure with total capex above US$2.2 billion or a capacity other than 1.5 MTPA; a profit-gas split that gives the State less than the royalty; a chartered vessel whose rate adds materially to opex; or a reserve report that puts the 1.5 Tcf headroom outside Block 52’s commercial field. Each would change the numbers here and should trigger a re-run.
Drs. Marcel P.T. Chin-A-Lien, MBA, M.Sc., Ing., geologist, is Principal Founding Partner and Chief Architect of GLIAG. AAPG Certified Petroleum Geologist #5201-1996; EFG European Geologist #92-1996; AIEN Energy Negotiator. He works from Zoetermeer and Paramaribo on the petroleum systems, fiscal design and development strategy of the Guyana–Suriname Basin, and designed the GLIAG GSB Intelligence Platform (GIP). ORCID 0009-0007-1649-602X.
GLIAG (Golden Lane Investments Advisory Group) is an independent petroleum, energy and strategic-advisory platform focused on Suriname, Guyana and the wider Caribbean–South American region. It acts as Owner’s Engineer, project-management consultant and strategic adviser to governments, national oil companies, development-finance institutions and investors, and develops GIP. www.gliag.com · petroleumenergyinsights.com · info@gliag.com
The author leads GLIAG. This essay was not commissioned or reviewed by PETRONAS, PETRONAS Suriname E&P B.V., Staatsolie, Paradise Oil Company or the Government of Suriname. GLIAG is not a sponsor of, or equity investor in, Block 52, KrakaWi or any project or licence discussed.
AI disclosure. Perplexity Computer, an AI agent system, assisted with source verification, an independent rebuild of the screening model, editing, figure preparation and document preparation under the author’s direction. It is not an author; the author is responsible for the content.
Licence and rights. © 2026 Marcel P.T. Chin-A-Lien and GLIAG Intelligence B.V. Licensed under CC BY-NC-ND 4.0 (creativecommons.org/licenses/by-nc-nd/4.0). Golden Lane™, GLIAGOGRAPH™, Sovereign Molecule™, Sovereign Conversion Capacity™ and Caribbean Gas Arc™ are designations of GLIAG; the National Pre-FID Gate doctrine is a GLIAG framework. Third-party material quoted or linked remains the property of its owners. The rights holders expressly reserve the rights of reproduction and extraction for text and data mining, including the training of artificial-intelligence systems, under Article 4(3) of Directive (EU) 2019/790.
GLIAG · Born in knowledge. Built for decisions.
Insights. Viable Solutions. Resilient Value.
Converting bare headlines into deep strategic, added value · GLIAG · Where Information Becomes Intelligence
Zoetermeer & Paramaribo · 26 November 2026
Soso Lobi
An audit of GLIAG’s 2 July 2026 Sloanea screening model against the 26 November KrakaWi…
PetroChina's record nine-month 2026 cash flow makes a shallow-water Suriname well readily fundable, and its…
The President's Office has invited the media to a Block 52 meeting with PETRONAS on…
Could PETRONAS move PFLNG DUA from Rotan to Sloanea, Block 52 offshore Suriname? A credible…
Vier GLIAG-presentaties in Paramaribo, van 16 tot 20 november 2026: SPE Suriname Section, KKF, De…
Guyana en Suriname vormen één bekken met één migratieroute; er is veel meer olie gevormd…