Sloanea's FLNG choice: could PFLNG DUA move from Rotan to Suriname? Credible hypothesis, not an announced decision.

Sloanea’s FLNG Choice: PFLNG DUA Reuse, Alternatives and What the FID Must Contain for a Viable Gas-to-Shore

GLIAG STRATEGIC INTELLIGENCE · SCREENING NOTE · WORKING PAPER · GLIAG-FE-2026-1120-SLN-001 · Revision 1.0 · 20 November 2026 · Zoetermeer & Paramaribo

PFLNG DUA reuse, alternatives, project economics, the Malaysian–Surinamese legal comparison and what the FID must contain for a viable Gas-to-Shore

ZENODO VERSION OF RECORD

DOI: https://doi.org/10.5281/zenodo.24407620

PDF (15 pages): download from Zenodo · Licence CC BY-NC-ND 4.0 · TDM reserved, Art. 4(3) Directive (EU) 2019/790

Author: Drs. Marcel P.T. Chin-A-Lien, MBA, M.Sc., Ing., geologist · Principal Founding Partner and Chief Architect, GLIAG · AAPG Certified Petroleum Geologist #5201-1996 · EFG European Geologist #92-1996 · AIEN Energy Negotiator · ORCID 0009-0007-1649-602X

Sloanea's FLNG choice: could PFLNG DUA move from Rotan to Suriname? Credible hypothesis, not an announced decision.
GLIAG-GRAPH-2026-11-20-SLOANEA-01, GLIAG Intelligence Platform. Illustrative; not a site map or engineering drawing.

Status of this edition. Revision 1.0 is the public edition of the GLIAG screening note dated 20 November 2026. The original analysis is kept; it is amended only where new or re-checked evidence required it, and Section 8 is new. Every change is listed in Annex C. As at 20 November 2026 no Final Investment Decision (FID) for Sloanea and no FLNG vessel selection has been announced by PETRONAS or Staatsolie. The cover graphic is labelled accordingly: credible hypothesis, not an announced decision.

Executive judgement

PFLNG DUA is a credible, publicly evidenced candidate for a PETRONAS FLNG reuse case at Sloanea, Block 52 offshore Suriname, but it is one of three live options rather than a settled choice. The key clue is a public profile of a JGC process engineer, which lists a “PFLNG DUA Relocation project – FEED (Petronas)” from May 2026 and describes moving the unit from Rotan to Sloanea, with adequacy checks and modifications for new feed gas. This is unusually specific, but it is an individual project-history entry, not a PETRONAS, JGC or Staatsolie project announcement. It supports a serious working hypothesis, not a confirmed selection. [1]

That clue conflicts with Energy Intelligence’s March 2026 reporting that the project was likely to use PFLNG SATU, then described as “the only relocatable floater” in the PETRONAS fleet. It also sits beside a third route: in April 2025 Wison New Energies signed a definition study for a newbuild FLNG for Block 52. [4] [12]

Water depth no longer favours DUA as cleanly as the first draft suggested. Sloanea lies about 120 km offshore in roughly 450 m of water. [12] [19] The SOFEC turret designer’s data show the DUA external turret was designed for 500–1,500 m water depth (first deployment at Rotan, about 1,250 m) and the SATU turret for 70–200 m. [13] Sloanea is therefore outside the original mooring envelope of both PETRONAS floaters: about 50 m shallower than DUA’s design minimum and about 250 m deeper than SATU’s maximum. Either reuse case needs a new or re-engineered mooring and riser system. GLIAG’s view is that DUA remains the closer depth fit and the better capacity match, but that the depth argument is now a design question, not a deciding fact.

Rotan should not be described as publicly proven depleted. PETRONAS reports first gas on 6 February 2021, a 270 MMscf/d target and a gas-sales arrangement designed for approximately ten years. Those facts indicate planned long-term supply, not remaining reserves or the actual depletion curve. A DUA transfer to Suriname therefore requires an explicit Rotan offtake and production-transition plan. [5] [6]

The FID is close. On 20 November 2026 ABC Suriname reported an industry expert’s view that PETRONAS may sign the Block 52 gas development contract around 25 November 2026 (Srefidensi), using an existing FLNG adapted for Suriname, with production from 2030. This is a media report of an expert opinion, not an official statement. [17] Whatever the vessel, the FID package is the last low-cost point at which Suriname can secure a viable Gas-to-Shore (GtS) option. Section 8 sets out what that package should contain.

CONCLUSION IN ONE LINE · DUA reuse is a credible hypothesis for Sloanea, but the vessel identity, mooring solution, economics and schedule are not confirmed. Proceed only after the Development Plan and FID package disclose a verified vessel-selection, life-extension, gas-supply and contract case, and contain the Gas-to-Shore provisions in Section 8 before any LNG sales agreement locks the gas into export.

1. What is known, and what is not

Staatsolie’s public account says Sloanea-1 was discovered in 2020, the Sloanea-2 appraisal in 2024 confirmed gas-in-place and recoverable volumes, and the selected concept comprises gas development wells, subsea infrastructure and an FLNG facility. Staatsolie approved the commercial field on 11 November 2025 and announced it on 13 November 2025. It does not publish the recoverable-volume figure or name the FLNG hull. The plan was to submit a Development Plan and target FID in the second half of 2026, with first gas expected in 2030; Staatsolie’s Annual Report 2025 repeats an FID expected by the end of 2026 and records that a Gas Master Plan has been prepared. [3] [16]

Block 52 is held by PETRONAS Suriname (80%, operator) and Paradise Oil Company, a Staatsolie subsidiary (20%), under the April 2013 PSC and its gas addendum. [3] [27] Since the declaration of commerciality the block has grown: on 30 June 2026 PETRONAS reported that eight successful Block 52 wells had together found more than 1 billion boe of recoverable resources, and that SAC-1, about 8 km east of Sloanea-1 in about 610 m of water, found gas-bearing reservoirs with strong deliverability on drill-stem test. [15] On 27 May 2026 Staatsolie’s managing director told Reuters that a declaration of commerciality for oil in Block 52 could follow within about 18 months. [11]

Energy Intelligence reported on 17 March 2026, from an interview with Staatsolie’s managing director, a phased concept starting with two to three development wells and a refurbished or leased existing vessel, possibly allowing first gas before 2030, with Staatsolie seeking financing for its 20% interest and planning an LNG trading capability. [4] In April 2026 PETRONAS Suriname signed a long-term subsea collaboration agreement with SLB OneSubsea and Subsea7 covering subsea production systems, umbilicals, risers and flowlines for multiple discoveries. [26] As at 26 October 2026 the FID had not been announced and whether any gas would come ashore had not been decided. [18]

Evidence item What it supports Weight and limit
PETRONAS official fleet page and DUA naming release PFLNG SATU and DUA are operating units; published capacity and depth specifications; DUA moored at Rotan in about 1,300 m, 140 km off Kota Kinabalu. [2] [28] Primary source for fleet specifications; does not say which unit is allocated to Sloanea.
SOFEC turret data (Gastech 2018) DUA turret design depth 500–1,500 m, 300 MMscf/d total throughput, 4 × 10-inch risers; SATU turret 70–200 m, 208–230 MMscf/d. [13] Designer’s published design basis; the as-built and current certification may differ.
JGC engineer’s public profile “PFLNG DUA Relocation project – FEED (Petronas)”, May 2026 onward; Rotan-to-Sloanea move and feed-gas modifications. [1] Specific, timely clue; individual profile, not an award notice. The profile exists (JGC India, Associate Process Engineer); the project entry could not be re-read without a LinkedIn login on 20 November 2026.
Energy Intelligence, 17 March 2026 SATU reported as the likely existing-vessel option; phased concept; financing and LNG trading plans. [4] Credible industry reporting; earlier than the DUA FEED entry and not a company confirmation.
Wison New Energies, 25 April 2025 Definition study for a newbuild FLNG for Block 52, about 120 km offshore, about 450 m water depth, LNG and condensate “for domestic and export”. [12] Contractor release; a study award, not a construction contract. Source of the 120 km and 450 m figures.
PETRONAS Rotan releases Rotan-Buluh first gas, 270 MMscf/d target, about ten-year GSA. [5] [6] Useful on Rotan supply; do not confirm a Suriname transfer or remaining reserves.
Staatsolie Sloanea announcement and Annual Report 2025 Commerciality, gas addendum, FLNG concept, FID and first-gas expectations, Gas Master Plan. [3] [16] Primary project source; no hull identity, gas balance or economics.
ABC Suriname, 20 November 2026 Expert view that signing may occur around 25 November 2026 with an adapted existing FLNG. [17] Media report of an opinion; not confirmed by PETRONAS or Staatsolie.

2. Facility comparison for Sloanea

Option Published or reported facts Sloanea fit Main consequence
PFLNG DUA (reuse) 1.5 MTPA; PETRONAS states depth capability up to 1,500 m; turret designed for 500–1,500 m; 300 MMscf/d total throughput; at Rotan since 2020, first LNG February 2021; 20-year design life. [2] [13] [28] Closer depth fit, but about 50 m below the turret’s design minimum at a reported 450 m site. Its 1.5 MTPA nameplate is a useful scale reference. Gas composition, feed pressure, subsea interface, mooring, risers and remaining life still need FEED validation. Potentially lower cost and faster delivery than a newbuild; transfer, overhaul, mooring and riser redesign, life extension, Rotan supply replacement and modification scope can erode the savings.
PFLNG SATU (reuse) 1.2 MTPA; turret designed for 70–200 m; first LNG 2016; completed the world’s first FLNG relocation, Kanowit to Kebabangan, in March 2019. [2] [13] [14] Published depth envelope is about 250 m shallower than Sloanea. A use case needs a verified engineering basis: a new deeper-water mooring and riser system or a different site assumption. Proven relocation record and smaller scale suit a phased start of two to three wells. The depth mismatch is a material screening issue; retain SATU as a live alternative because industry reporting named it. [4]
Newbuild FLNG Wison definition study for Block 52 signed April 2025; capacity, design basis and cost would be set for Sloanea; De Ware Tijd reports an FLNG cost of at least USD 1 billion. [12] [19] Best opportunity to optimise process train, capacity, feed envelope, emissions, metocean and service life for Sloanea, and to build in Gas-to-Shore tie-in provisions from the start. Likely highest upfront spend and longest fabrication path; reduces legacy-condition risk. The actual premium and schedule cannot be stated without bids or FEED.

Depth is a screening factor, not a conclusion. “Up to 1,500 m” is a published facility capability; it is not proof that DUA’s existing mooring, risers, turret, anchors, hull condition or safety case can be approved for Sloanea. Both reuse options need a site-specific station-keeping design, because 450 m lies between the two published turret envelopes. [13] GLIAG’s view is that the decisive variables are now remaining hull and topsides life, the cost of a new mooring and riser package, and the Rotan release date, not the headline depth rating.

3. Rotan: production history is not a depletion statement

PETRONAS says first gas from Rotan and Buluh occurred on 6 February 2021. The Block H development was designed around 270 MMscf/d and DUA processing, with PETRONAS describing deliveries for approximately ten years under the Gas Sales Agreement. The PETRONAS releases reviewed do not establish the remaining recoverable reserves of Rotan alone. [5] [6]

A simple calendar calculation illustrates the issue, not the actual production history: 270 MMscf/d × 365 × 10 years is about 0.986 Tcf of gross gas at a constant target rate. By 20 November 2026, approximately 5.8 years have elapsed since first gas, leaving roughly 4.2 calendar years in a nominal ten-year period. Actual output can differ because of ramp-up, uptime, field decline, contract terms and the Rotan/Buluh contribution split. This arithmetic cannot be cited as reserves produced or as remaining reserves.

Accordingly, DUA relocation could occur before Rotan is depleted, if remaining gas is handled through another route, if the GSA or supply plan is renegotiated, or if DUA’s contract allows an earlier release. It could also be delayed until supply declines or alternative processing is ready. The relevant diligence is the actual monthly gas-delivery series, decline forecast, remaining recoverable volumes, GSA expiry and termination rights, and the replacement processing or export plan, not a generic assumption that a field is old.

4. What must be re-engineered for Sloanea

Relocating an FLNG is a project, not simply towing a vessel. The DUA clue itself says FEED must verify vessel adequacy and modify it for different feed-gas conditions. A credible Sloanea scope would include the following work items, each with a design document that the FID package should reference. [1] [13]

  • Reconfirm LNG capacity against Sloanea’s undisclosed recoverable volumes, well deliverability and decline profile, including SAC-1 if it is tied in; test both nameplate and turndown cases.
  • Characterise feed gas composition, liquids, CO₂, nitrogen, mercury, water, contaminants, pressure and temperature; compare against DUA’s process design and establish pretreatment changes.
  • Design new wells, subsea trees, manifolds, flowlines, risers, umbilicals and control systems for about 450 m of water, then validate hydraulics, slugging, hydrate management and restart scenarios.
  • Design a new or modified mooring and riser system for a site outside the original turret envelope; survey hull, process equipment, rotating machinery, containment, turret, fatigue life, corrosion and safety systems; set refurbishment, life-extension and spares scope.
  • Complete site-specific metocean, geotechnical, anchoring, station-keeping, marine traffic, LNG carrier approach and offloading analyses at Sloanea.
  • Plan disconnection at Rotan, yard work, towing, reinstallation, hook-up, commissioning, regulatory approvals, insurance and emergency response; test the integrated system before first LNG.
  • Reserve the physical interfaces for a later Gas-to-Shore line (Section 8): a spare riser or J-tube slot or a subsea export tee, and a defined sales-gas specification and metering point.

The proposed 2030 first-gas date gives a reason to consider reuse, but it does not prove that reuse will be faster. The critical path may sit in upstream wells, subsea systems, long-lead equipment, approvals, yard availability or commissioning. A schedule comparison needs a dated integrated project plan, not a generic claim that reuse is faster.

5. Economics: transparent screening case

No public Sloanea FEED estimate, DUA relocation budget, newbuild bid, LNG sales contract, full fiscal model or audited Sloanea development profile was identified. The following is therefore a sensitivity illustration of gross sales scale only. It is not a project valuation, forecast, or claim about PETRONAS’s expected price.

Illustrative input Assumption
FLNG nameplate 1.5 million tonnes LNG per year (DUA published capacity)
Utilisation 90% of nameplate = 1.35 million tonnes per year
Energy conversion 52 MMBtu per tonne of LNG; planning assumption
Annual LNG energy 1.35 million tonnes × 52 = 70.2 million MMBtu per year
Illustrative realised LNG price USD 8.50 / 10.50 / 12.00 per MMBtu (nominal); scenario only
Illustrative price Gross annual LNG sales value What the number excludes
USD 8.50/MMBtu USD 597 million Gas value and cost, capex, operating and shipping costs, taxes, royalties, financing, abandonment and price and volume risks.
USD 10.50/MMBtu USD 737 million Same exclusions; this is gross LNG sales value, not project cash flow or state revenue.
USD 12.00/MMBtu USD 842 million Same exclusions; does not establish contract price, profitability or fiscal take.

Condensate revenue is excluded; Wison’s study scope includes condensate, so the liquids stream may add value that this table does not show. [12] The same plant also implies a gas requirement. Using the SOFEC design throughputs (SATU 208 MMscf/d at 1.2 MTPA; DUA 300 MMscf/d total at 1.5 MTPA), a 1.35 MTPA operation needs roughly 230–270 MMscf/d of raw feed gas, or about 1.7–2.0 Tcf over 20 years. [13] This is a GLIAG calculation, not a reserves figure. It matters for Gas-to-Shore: any domestic tranche must come from volumes above, or carved out of, that LNG requirement.

The economic value of DUA reuse is the verified difference between (a) newbuild or other alternative capital and schedule cost and (b) relocation, refurbishment, life-extension, mooring and riser, interface, offshore installation, Rotan transition and risk-adjusted operating cost. Reuse creates value only if its capex and schedule savings exceed those added costs and do not reduce recoverable LNG volumes or uptime. A decision-grade comparison requires discounted cash flow using the same production profile, gas price, fiscal terms, financing assumptions, contingency and decommissioning basis for all options.

For Suriname, a lower facility bill is not automatically a higher public benefit. The PSC’s cost-recovery and profit-sharing mechanics, the price and allocation of gas, Staatsolie/POC’s participating-interest funding, LNG marketing terms, tariffs, domestic reservation, tax and royalty treatment, and abandonment liability determine how savings are divided. De Ware Tijd reports that a memorandum of understanding gives PETRONAS a ten-year income-tax-free period from the start of gas production; if confirmed, the state’s early cash take rests on royalty (6.25% of gross offshore production under the Offshore Royalty Decree), profit gas and POC’s 20% share. [19] [23] The public record does not disclose enough of those terms for a defensible NPV or government-take estimate.

6. Malaysia’s petroleum and gas laws versus Suriname

There is no single Malaysian “Gas Act” that can simply be copied as Sloanea’s development law. Three instruments matter. The Petroleum Development Act 1974 (PDA, Act 144) vests petroleum ownership and exclusive rights in PETRONAS. The Gas Supply Act 1993 (Act 501) regulates the licensing and safety of gas supplied through pipelines; the Energy Commission states that its scope begins downstream of the city-gate station and that it applies in Peninsular Malaysia and Sabah. [7] [8] [24] The third, omitted from the first draft, is the Sarawak Distribution of Gas Ordinance 2016 (amended 2023), under which the state company PETROS was appointed sole gas aggregator in Sarawak. [20] [21] [22]

The Sarawak case is the most direct Malaysian precedent for Sloanea. On 21 May 2025 the Federal and Sarawak governments issued a Joint Declaration under which the PDA and the Ordinance coexist, PETROS acts as domestic gas aggregator in Sarawak excluding LNG, an allocation of 1.2 Bscf/d is set aside for Sarawak’s own use, and existing LNG contracts are honoured. [20] [21] In plain terms, a producing state with a large LNG export system fixed a domestic gas tranche and a domestic aggregator after export had begun, and had to protect the export contracts already in force. Suriname can do the same thing before its first LNG contract exists, which is cheaper and simpler.

Suriname’s model differs in institutional design. The Constitution, Mining Decree and Petroleum Law place petroleum resources in public ownership and route exclusive concession rights through state enterprises; Staatsolie contracts with private operators through PSCs. [9] [10] For Block 52 the parties added a gas addendum to the 2013 PSC after evaluating monetisation options. [3] The addendum itself is not public, so its domestic-gas, pricing, export, cost-recovery and decision rights should not be assumed.

The public Staatsolie model PSC shows why the addendum carries the weight. Its Domestic Supply Requirement (Article 20) is defined for crude oil only: the contractor can be asked to supply up to 25% of its entitlement at the crude basket price. For non-associated gas, Article 21.4 requires an addendum covering orderly development, the expected market price “in relation to its location, volume and potential customers”, Staatsolie’s participation and cost recovery and profit sharing. [25] The model text contains no domestic gas obligation, landing requirement or tie-in right. The 2013 Block 52 PSC may differ from the current model, but if it follows the same pattern, the gas addendum and the Development Plan approval are the only contractual places where a Gas-to-Shore tranche can be secured before FID.

Question Malaysia model Suriname/Sloanea implication
Who holds upstream rights? PDA vests petroleum rights in PETRONAS as the national petroleum corporation. [7] State ownership and Staatsolie’s concession and PSC role remain the basis; PETRONAS is contractor and operator under the Block 52 PSC. [9]
What does the gas-supply statute regulate? Act 501: licensing and safety of piped gas downstream of the city gate; not the instrument that allocates upstream gas. [8] [24] Suriname should separate upstream production and export approvals from downstream pipeline supply, network access, tariffs and safety. A future Gas Act should define each remit.
Who aggregates and allocates domestic gas? Sarawak: PETROS as sole domestic aggregator under the Distribution of Gas Ordinance; 1.2 Bscf/d domestic allocation; LNG excluded. [20] [22] Staatsolie or a designated subsidiary can act as single domestic buyer and aggregator; the tranche and priority rules belong in the gas addendum before LNG sales agreements.
How is Sloanea governed today? Not applicable. Petroleum framework, Block 52 PSC and gas addendum, the Development Plan once approved, permits and later sale and transport agreements. The model PSC has no gas domestic obligation; the addendum’s terms are not public. [25]
What should be adapted? PETRONAS’s consolidated statutory position is Malaysia-specific. Borrow functional principles: clear resource owner, capable national aggregator, transparent approvals, a defined domestic allocation and pipeline safety, without copying PETRONAS’s exclusive statutory ownership.

For Sloanea, the immediate legal task is to make the Development Plan and gas addendum operationally complete before FID. They should specify the FLNG ownership, charter or tolling model; relocation and life-extension accountability; gas measurement, quality and delivery points; domestic reservation and a transparent surplus-export test; a domestic pricing formula; cost recovery and audit rights; LNG lifting, marketing and destination arrangements; gas-supply interruption priorities; information disclosure; local-content and training commitments; decommissioning security; and dispute-resolution and step-in mechanisms. These are recommendations for contract and regulatory completeness, not a claim that current law already contains each provision.

A proposed Suriname Gas Act discussed in GLIAG’s policy essays is a policy recommendation, not enacted legislation as at 20 November 2026. It should complement, not silently override, the Petroleum Law, PSC and gas addendum. Any proposed statute must be harmonised with constitutional ownership, Staatsolie’s legal role, environmental permitting, electricity regulation, pipeline licensing and existing contractual protections.

7. Consequences for Sloanea and Suriname

  • Capital and timing. DUA reuse could reduce upfront facility investment and potentially bring first LNG forward, but only if refurbishment, mooring and riser redesign, integration and the Rotan transition are costed and scheduled transparently.
  • Capacity and reserves. DUA’s 1.5 MTPA scale implies roughly 1.7–2.0 Tcf of feed gas over 20 years (GLIAG calculation, Section 5). That must be matched to the approved Sloanea recoverable-volume report, SAC-1 and the deliverability profile; public sources do not disclose enough to prove the facility is right-sized or fully used.
  • Gas security and sovereignty. LNG exports can monetise deepwater gas, while domestic power and industrial users need enforceable allocation and delivery terms before export commitments consume the available supply.
  • Mobility cuts both ways. If DUA or SATU can be moved from Malaysia to Suriname, the same unit can later be moved away from Suriname. A Gas-to-Shore line that depends on the FLNG for gas treatment needs contractual continuity if the vessel leaves before the field is exhausted.
  • Revenue distribution. PETRONAS’s 80% and POC’s 20% participating interests do not by themselves reveal state cash flows. Cost recovery, LNG netback, marketing, any tax holiday, debt and POC funding determine the public return.
  • Operational exposure. A relocated operating unit carries condition and integration risks. Independent integrity certification, performance guarantees, uptime commitments and clear responsibility for overruns and defects protect project value.
  • Local capability. Set local-content obligations early for marine services, logistics, fabrication, maintenance, training and LNG operations, recognising that specialist FLNG overhaul may be done outside Suriname.

8. What the Sloanea FID must contain to make Gas-to-Shore viable

Gas-to-Shore (GtS) here means a pipeline and onshore reception system that lands a defined share of Block 52 gas in Suriname for power, refining utilities and industry. GLIAG’s Gas-to-Shore Pre-Feasibility Study is a GLIAG proposal, not a project approved by the Government of Suriname or Staatsolie. This section does not argue that GtS must be built in 2030. It sets out what the FID package must fix now so that a GtS line can be built later at reasonable cost, whatever FLNG vessel is chosen.

FACT. The Block 52 concept is FLNG export with subsea wells. [3] The model PSC has a crude-oil domestic supply obligation but none for gas. [25] Wison’s newbuild study describes LNG and condensate “for domestic and export”. [12] As at 26 October 2026 no decision had been taken on landing gas onshore. [18] Sloanea is about 120 km offshore in about 450 m of water, with Block 52 depths of about 60–1,000 m. [12] [29]

MISSING. The recoverable gas volume and production profile; the Sloanea gas composition; the gas addendum’s terms; the Gas Master Plan; an assessed domestic demand curve; the FLNG charter or ownership model; and any landing-point or pipeline-route study. [3] [16]

GLIAG JUDGEMENT. GLIAG’s view is that the FID will decide whether GtS stays an affordable option or becomes a renegotiation. After FID, the subsea layout, the FLNG riser slots, the gas balance and the LNG sales agreements are fixed; lenders take security over the gas and its revenues. A domestic tranche added after that point competes with financed export commitments, as the Sarawak settlement shows. [20] Before FID, the same provisions cost little: a reserved riser slot or subsea tee, a written sales-gas specification, a reserved volume and a pricing rule.

The table lists the minimum content. Items 1–6 are physical and volumetric; items 7–12 are commercial, legal and institutional.

# FID package element What it should state Why it matters for GtS
1 Gas balance with a domestic tranche Field-by-field recoverable gas (Sloanea, SAC-1), annual profile, LNG feed requirement and a named domestic volume in MMscf/d with start year and duration. Illustration: 50–100 MMscf/d for 20 years needs about 0.37–0.73 Tcf (GLIAG calculation). Without a written volume, there is nothing to reserve. The LNG plant alone may need 1.7–2.0 Tcf over 20 years (Section 5).
2 Physical tie-in provisions A spare riser or J-tube slot on the FLNG turret, or a subsea export tee or spur on the production manifold, sized for the domestic tranche; space and weight reserved for an export compressor or metering skid. DUA’s turret was built with four 10-inch risers. [13] Retrofitting a slot or tee after start-up means shutdown risk and high cost.
3 Sales-gas specification and treatment point Whether domestic gas is taken after acid-gas removal and dehydration on the FLNG or as raw gas at the seabed; dew point, CO₂, H₂S, mercury, water limits; delivery pressure. Decides whether Suriname needs an onshore treatment plant and what it costs.
4 Delivery point and metering Custody-transfer point, fiscal metering standard, allocation between LNG and domestic streams, audit rights. Domestic gas must be measured separately for cost recovery, royalty and price.
5 Pipeline corridor and landing point A route and landfall study for a line of about 120 km from about 450 m water depth to shore, a reserved seabed corridor that the field layout and anchor pattern keep clear, and a candidate landing site. Mooring lines and flowlines can block the shortest route. The corridor costs nothing to reserve before installation.
6 Phasing with later fields How SAC-1 and later Block 52 gas join the system; capacity and access rules for third-party gas. A GtS line sized only for Sloanea’s first phase may be undersized; open access lets later fields share it.
7 Domestic gas obligation in the addendum A Domestic Gas Supply Obligation: volume, duration, priority over uncontracted export gas, and a surplus-export test before new LNG sales agreements. Fills the gap left by the crude-only Article 20 of the model PSC. [25]
8 Pricing formula A transparent domestic price: netback or cost-plus with floor and cap, indexation, review dates; treatment in cost recovery and profit gas. Article 21.4 already requires a gas price “in relation to its location, volume and potential customers”. [25] A price set by formula is easier to finance than one set by negotiation later.
9 Offtaker and credit support A named aggregator (Staatsolie or a subsidiary, on the PETROS model) as single buyer; take-or-pay terms; credit support from creditworthy anchors such as power generation and the Tout Lui Faut refinery. Lenders to the pipeline and to the upstream project both need a creditworthy buyer.
10 Priority and curtailment rules Order of supply in shortfalls (domestic tranche, existing LNG cargoes, spot cargoes); compensation for curtailment; force majeure. Prevents domestic supply being cut first when output falls.
11 FLNG continuity and mobility If the vessel is chartered or relocated: notice period, step-in or buy-back options, obligation to keep supplying the domestic stream until a replacement exists, decommissioning security. A relocated vessel can be relocated again (Section 7).
12 Fiscal, financing and disclosure Treatment of shared facilities in cost recovery; whether the tax holiday reported by De Ware Tijd covers domestic sales [19]; a midstream entity and DFI financing path for the pipeline; publication of a summary of the addendum’s domestic terms. Defines who pays for the shared spine and lets government, Parliament and lenders check the domestic bargain.

These provisions are bankable only if they are bounded. GLIAG’s earlier work recommends that a domestic obligation apply within a cap, carry a transparent price and compensation for curtailment, and rest on state-side transport and credit support, so that the LNG project’s lenders can still price their risk. [A9] The GtS demand case (power, refinery, industry) still has to be proven in a feasibility study; reserving gas without creditworthy demand would create a stranded asset.

TRIGGER. GLIAG would change this assessment if (a) the published FID or Development Plan summary names a domestic volume, tie-in provisions and a pricing rule, in which case GtS moves from option to project definition; (b) PETRONAS and Staatsolie sign LNG sales agreements covering substantially all recoverable gas before a domestic tranche is fixed, in which case GtS would depend on later fields or renegotiation; (c) an oil declaration of commerciality in Block 52 brings associated gas into the balance [11]; or (d) the vessel chosen has no spare riser capacity and no subsea tee is provided.

9. Decision gates before calling DUA “selected”

  • Official confirmation from PETRONAS, Staatsolie or the approved Block 52 Development Plan naming the FLNG hull and commercial arrangement.
  • Independent condition survey and remaining-life assessment for hull, containment, mooring and turret, process trains and safety-critical systems.
  • Site-specific engineering confirmation for water depth (about 450 m, outside both published turret envelopes), metocean, geotechnical conditions, mooring, risers, LNG offtake and safe operations.
  • Sloanea reservoir and reserves basis and production profile, including SAC-1, annual gas volume, condensate, decline, downtime, plateau duration and facility utilisation.
  • Rotan-Buluh production forecast and GSA transition plan: volumes, alternatives after DUA departure, rights to relocate and any replacement processing capacity.
  • Like-for-like capex, schedule, NPV and government-cash comparison for DUA reuse, SATU reuse and a newbuild; disclose contingency, life-extension, financing and abandonment assumptions.
  • Publication of a summary of the gas addendum’s economic and domestic-supply terms, with commercial confidentiality protected but core sovereign obligations visible, including the Section 8 items.

Conclusion

The strongest public clue is that PETRONAS and JGC began FEED work in 2026 on relocating PFLNG DUA from Rotan to Sloanea. [1] DUA’s 1.5 MTPA capacity makes it a good scale match, but its turret was designed for 500–1,500 m and Sloanea lies at about 450 m, so neither PETRONAS floater fits without a new mooring and riser solution. [13] Earlier reporting favoured SATU, and a newbuild study exists. [4] [12] The responsible conclusion is “credible hypothesis”, not “announced decision”.

Economically, DUA could strengthen Sloanea if verified reuse savings survive refurbishment, relocation, re-mooring, remaining-life and Rotan supply costs. Legally, Suriname should use Malaysia as a functional comparator. The PDA shows national vesting; Act 501 shows downstream pipeline regulation; and the Sarawak Ordinance shows how a domestic aggregator and tranche can be fixed, at higher cost when export contracts already exist. [7] [8] [20] Before FID, the selected vessel, gas balance, cost model, domestic allocation, tie-in provisions, LNG marketing and lifecycle liabilities need to be explicit enough for Staatsolie, POC, government and the public to see who carries the risk and who captures the value. For a viable Gas-to-Shore option, the twelve items in Section 8 are the test of that package.

Appendix A. Related GLIAG essays and working papers

The following are Marcel Chin-A-Lien / GLIAG publications. They are linked for context and continuity; they are the author’s analysis, not independent verification of the vessel selection.

Appendix B. References

[1] Shasti Muthu Booban B., JGC, public LinkedIn profile. “PFLNG DUA Relocation project – FEED (Petronas)”, May 2026–present; states Rotan-to-Sloanea scope and modifications for new feed-gas conditions. Individual profile, not official project confirmation. https://in.linkedin.com/in/shasti-muthu-booban-b-9a547a166

[2] PETRONAS, “Liquefied Natural Gas”. Official PFLNG SATU and DUA overview and published capacity and depth specifications. https://www.petronas.com/progressing-energy/liquefied-natural-gas

[3] Staatsolie, “Staatsolie approves Commercial Field for Sloanea-1 Gas Discovery in Block 52”, 13 November 2025. Development concept, gas addendum, recoverable volumes confirmed without public quantity, FID and first-gas targets. https://www.staatsolie.com/en/news/staatsolie-approves-commercial-field-for-sloanea-1-gas-discovery-in-block-52/

[4] Energy Intelligence, “Staatsolie Seeks FLNG Project Funding, Aims to Trade LNG”, 17 March 2026. Reports existing SATU as likely, a phased two-to-three-well start, financing and LNG trading plans; not a formal award. https://www.energyintel.com/0000019c-afe0-df3a-a59c-bffc7c520000

[5] PETRONAS Malaysia Petroleum Management, “PETRONAS Achieves Deepwater Gas Production Success Amidst Pandemic Challenges”. Rotan/Buluh wells, 270 MMscf/d deliveries and approximately ten-year GSA period. https://www.petronas.com/mpm/media/media-releases/petronas-achieves-deepwater-gas-production-success-amidst-pandemic-challenges

[6] PETRONAS, “First Deepwater Gas Production From Block H Offshore Malaysia Augments Malaysia’s Investment Potential”, 16 February 2021. First gas 6 February 2021 and target 270 MMscf/d. https://www.petronas.com/bm/node/69

[7] Attorney General’s Chambers of Malaysia, Petroleum Development Act 1974 (Act 144), official Laws of Malaysia text. https://lom.agc.gov.my/ilims/upload/portal/akta/LOM/EN/Act%20144%20-%20Petroleum%20Development%20Act%201974.pdf

[8] Suruhanjaya Tenaga (Energy Commission), Gas Supply Act 1993 (Act 501), as at 1 July 2017. https://www.st.gov.my/sites/default/files/2026-02/Act-501—Gas-Supply-Act-1993.pdf

[9] Staatsolie, Petroleum Law 1990 (S.B. 1991 No. 7), unofficial English translation. https://www.staatsolie.com/media/htzpfxtd/petroleum-law.pdf

[10] Staatsolie, “Legislation”: Constitution, Mining Decree, Petroleum Law and model PSC. http://www.staatsolie.com/en/shi/legislation/

[11] Reuters, “Suriname’s Block 52 could become commercial for oil in 18 months, Staatsolie says”, 27 May 2026. https://www.reuters.com/business/energy/surinames-block-52-could-become-commercial-oil-18-months-staatsolie-says-2026-05-27/

[12] Wison New Energies, definition study for a newbuild FLNG for Suriname Block 52, 25 April 2025: about 120 km offshore, about 450 m water depth, LNG and condensate for domestic and export. https://www.wison-energies.com/News/1270.aspx

[13] Duggal, A. (SOFEC), “Selection and Optimization of FLNG Mooring Systems”, Gastech, 19 September 2018. PFLNG SATU and DUA turret design bases. https://www.sofec.com/wp-content/uploads/presentations/2018-Gastech-Selection-and-Optimization-of-FLNG-Mooring-Systems.pdf

[14] Journal of Petroleum Technology, “PETRONAS Ships First LNG From New Deepwater FLNG”, 2021. SATU 70–200 m, 1.2 MTPA, first FLNG relocation in March 2019. https://jpt.spe.org/petronas-ships-first-lng-from-new-deepwater-flng

[15] The Star, “Petronas records three new successes in Suriname’s Block 52”, 30 June 2026. Eight successful wells, more than 1 billion boe recoverable, SAC-1. https://www.thestar.com.my/business/business-news/2026/06/30/petronas-records-three-new-successes-in-surname039s-block-52

[16] Staatsolie, Annual Report 2025. FID expected by end-2026; Gas Master Plan; financing strategy for the participating interest. http://www.2026.staatsolie.com/legacy-media/ecclncfm/staatsolie-annual-report-2025-web.pdf

[17] ABC Suriname, “FID Petronas mogelijk rond Srefidensi over gasontwikkeling Blok 52”, 20 November 2026. https://abcsuriname.com/fid-petronas-mogelijk-rond-srefidensi-over-gasontwikkeling-blok-52/

[18] Suriname Business, “Suriname offshore oil blocks”, status as at 26 October 2026. https://surinamebusiness.com/en/suriname-offshore-oil-blocks

[19] De Ware Tijd, “Suriname verwacht tweede investeringsbesluit dit jaar”, 2026. Ten-year tax-free period from start of gas production under an MoU; FLNG cost of at least USD 1 billion; 120 km, about 450 m. https://dwtonline.com/suriname-verwacht-tweede-investeringsbesluit-dit-jaar

[20] Sarawak Premier’s Department (UKAS), Joint Declaration of the Federal and Sarawak Governments on gas, 21 May 2025. https://premierdept.sarawak.gov.my/web/subpage/news_view/18320/UKAS

[21] The Edge Malaysia, report on the PETROS gas aggregator arrangement and Joint Declaration, 2025. https://theedgemalaysia.com/node/824743

[22] Sarawak, Distribution of Gas Ordinance 2016, LawNet text. https://lawnet.sarawak.gov.my/lawnet_file/Ordinance/ORD_Distribution%20of%20Gas%20LawNet.pdf

[23] Staatsolie, Besluit Offshore Royalty (S.B. 2005 No. 52): royalty of 6.25% of gross offshore production. https://www.staatsolie.com/media/zk4hxo0n/besluit-offshore-royalty.pdf

[24] Suruhanjaya Tenaga, guidebook on the Gas Supply Act 1993: scope downstream of the city-gate station; applicable in Peninsular Malaysia and Sabah. https://meih.st.gov.my/documents/10620/61a1e3cc-e26b-4a0c-a83a-d8dfaf568fcd

[25] Staatsolie, Model Production Sharing Contract, Articles 20 (Domestic Supply Requirement) and 21 (Natural Gas). http://www.staatsolie.com/media/tuvjyme3/model-psc.pdf

[26] SLB / Business Wire, “SLB OneSubsea and Subsea7 Sign Collaboration Agreement with PETRONAS Suriname”, April 2026. https://www.sttinfo.fi/tiedote/71937252/slb-onesubsea-and-subsea7-sign-collaboration-agreement-with-petronas-suriname?publisherId=58763726&lang=en

[27] Offshore Energy, “PETRONAS clears key milestone for Suriname’s first offshore gas development”, 14 November 2025. https://www.offshore-energy.biz/2025/11/14/petronas-clears-key-milestone-for-surinames-first-offshore-gas-development

[28] PETRONAS, “PETRONAS Names Its Second Floating LNG Facility”, 2019. DUA to be moored at Rotan in 1,300 m, 140 km offshore Kota Kinabalu, 1.5 MTPA. https://www.petronas.com/media/media-releases/petronas-names-its-second-floating-lng-facility

[29] The Malaysian Reserve, “Petronas-led Suriname block may achieve oil viability in 18 months”, 28 May 2026. Block 52 about 4,750 km², water depths about 60–1,000 m. https://themalaysianreserve.com/2026/05/28/petronas-led-suriname-block-may-achieve-oil-viability-in-18-months-report

Annex C. Amendment register (draft of 20 November 2026 to Revision 1.0)

# Location Draft text or gap Amendment and basis
C1 Executive judgement, §2, Conclusion DUA described as “the more natural technical fit” and “best apparent depth fit” for a site “commonly reported” at 450 m. Corrected: DUA turret designed for 500–1,500 m and SATU for 70–200 m, so 450 m is outside both envelopes; DUA is closer, not a native fit. Source for 450 m and 120 km now named. [12] [13]
C2 §1, §2 Newbuild described with “no public Sloanea newbuild award”. Added Wison newbuild FLNG definition study, 25 April 2025, and De Ware Tijd cost indication. A study award, not a construction award; the original statement on awards stands. [12] [19]
C3 §1 Block 52 data limited to Sloanea. Added SAC-1, eight successful wells, more than 1 billion boe, Annual Report 2025, Gas Master Plan, SLB/Subsea7 agreement, FID status as at 20 November 2026. [15] [16] [17] [18] [26]
C4 §1 Energy Intelligence summarised as “SATU likely”. Added the phased concept, two to three initial wells, financing and LNG trading plans from the same report. [4]
C5 §2 SATU relocation history not stated. Added world’s first FLNG relocation, March 2019. [14]
C6 §3 Unsourced reference to PTTEP reporting. Removed; no PTTEP source in the reference list.
C7 §5 Feed-gas requirement and condensate absent; no fiscal holiday. Added GLIAG feed-gas calculation (230–270 MMscf/d; 1.7–2.0 Tcf over 20 years), condensate exclusion, reported ten-year tax-free period and royalty rate. [13] [19] [23]
C8 §6 Act 501 described generally; Sarawak omitted. Added Act 501 scope (downstream of city gate; Peninsular Malaysia and Sabah), Sarawak Distribution of Gas Ordinance, PETROS and the 21 May 2025 Joint Declaration. [20] [21] [22] [24]
C9 §6 No analysis of PSC gas terms. Added model PSC Article 20 (crude-only domestic supply) and Article 21.4 (gas addendum content). [25]
C10 §7 Mobility risk absent. Added “Mobility cuts both ways”.
C11 New §8 No Gas-to-Shore FID content. Added FACT · MISSING · GLIAG JUDGEMENT · TRIGGER assessment and a twelve-item FID package list.
C12 Appendix A Link to a private library item. Replaced by a plain description; private links are not published. Added [A12] and [A13].
C13 References Two dead links ([8], [10]). Replaced with current official URLs; 18 references added ([12]–[29]).
C14 Title block “Prepared for Marcel P.T. Chin-A-Lien”. Authorship stated per GLIAG protocol; subtitle extended to name the FID question.

Method and limitation

Public-source screening as at 20 November 2026. The note distinguishes official records, contractor and designer publications, industry and media reporting, and an individual professional profile. No confidential FEED, Development Plan, PSC gas addendum, reservoir report, DUA condition survey, bid, LNG sales contract or project cash-flow model was available. The economic and feed-gas calculations are illustrative GLIAG calculations and cannot substitute for operator or regulator diligence. Figures are not reserves or resources certification.

Suggested citation

Chin-A-Lien, M.P.T. (2026). Sloanea’s FLNG Choice: PFLNG DUA reuse, alternatives, project economics, the Malaysian–Surinamese legal comparison and what the FID must contain for a viable Gas-to-Shore. GLIAG-FE-2026-1120-SLN-001, Revision 1.0, 20 November 2026. GLIAG, Zoetermeer & Paramaribo. Zenodo. https://doi.org/10.5281/zenodo.24407620

About the author

Drs. Marcel P.T. Chin-A-Lien, MBA, M.Sc., Ing., geologist, is Principal Founding Partner and Chief Architect of GLIAG. AAPG Certified Petroleum Geologist #5201-1996; EFG European Geologist #92-1996; AIEN Energy Negotiator. He works from Zoetermeer and Paramaribo on the petroleum systems, fiscal design and development strategy of the Guyana–Suriname Basin, and designed the GLIAG Intelligence Platform (GIP). ORCID 0009-0007-1649-602X.

About GLIAG

GLIAG (Golden Lane Investments Advisory Group) is an independent petroleum, energy and strategic-advisory platform focused on Suriname, Guyana and the wider Caribbean–South American region. It acts as Owner’s Engineer, project-management consultant and strategic adviser to governments, national oil companies, development-finance institutions and investors, and develops GIP. www.gliag.com · petroleumenergyinsights.com · info@gliag.com

Competing interests

The author leads GLIAG, which has authored the Gas-to-Shore Pre-Feasibility Study proposal referred to in Section 8. That study is a GLIAG proposal, not an approved project of the Government of Suriname or Staatsolie. This note was not commissioned or reviewed by PETRONAS, Staatsolie, Paradise Oil Company, JGC, Wison, SOFEC or the Government of Suriname. GLIAG is not a sponsor of, or equity investor in, any project or licence discussed.

Disclaimer and legal notice

  1. No advice. This note is analysis, not investment, legal, tax or accounting advice. Readers should take their own professional advice.
  2. No offer or solicitation. Nothing in this note is an offer to sell or a solicitation of an offer to buy any security.
  3. Independence of analysis. GLIAG prepared this analysis independently. It is not commissioned, reviewed or endorsed by PETRONAS, Staatsolie, Paradise Oil Company, JGC, Samsung Heavy Industries, Wison New Energies, SOFEC, the Government of Suriname, the Federal Government of Malaysia, the Government of Sarawak, PETROS or any institution or publication named or linked.
  4. Forward-looking statements. Projections, estimates and calculations depend on assumptions that may prove wrong, including vessel selection, FID timing, gas volumes, gas allocation, prices, fiscal terms and construction costs. Actual results may differ materially.

AI disclosure. Perplexity Computer, an AI agent system, assisted with source verification, editing and document preparation under the author’s direction. It is not an author; the author is responsible for the content.

Licence and rights. © 2026 Marcel P.T. Chin-A-Lien and GLIAG Intelligence B.V. Licensed under CC BY-NC-ND 4.0. The rights holders expressly reserve the rights of reproduction and extraction for text and data mining under Article 4(3) of Directive (EU) 2019/790.

Cover graphic. GLIAG-GRAPH-2026-11-20-SLOANEA-01, GLIAG Intelligence Platform. Illustrative; not a site map or engineering drawing.